Nashua - Merrimack - Bedford 13761
>> Click here for latest News Release
Project 13761A
Turnpike Widening from North of Exit 8, in Nashua, to South of Exit 10 in Merrimack”
Recent Activities – As of early November 2024
• Northbound
– Milling, paving, and drainage work in the median in preparation for Phase 2 traffic shift south of the Pennichuck Brook bridge.• Southbound
– No work at this area.• Exit 10
– Constructed temporary northbound off-ramp.– Began demolition of toll tunnels.
• Pennichuck Brook Bridge
– The 180-day settlement period is on-going.Upcoming Work – November 2024 to December 2024
• Northbound
– Finish paving and striping south of the Pennichuck Brook bridge and place traffic in Phase 2 TCP configuration.– Begin tree clearing.
– Continue Phase 2 mainline drainage and widening work.