Nashua - Merrimack - Bedford 13761
>> Click here for latest News Release
Project 13761A
Turnpike Widening from North of Exit 8, in Nashua, to South of Exit 10 in Merrimack”
Recent Activities – As of early December 2024
• Northbound
– Traffic has been shifted into Phase 2 configuration.• Southbound
– No work at this area.• Exit 10
– NB Off-Ramp traffic is in the temporary configuration.– Old toll tunnels have been prepped for demolition.
• Pennichuck Brook Bridge
– The settlement period has completed.– Began excavation for bridge foundations.
Upcoming Work – November 2024 to December 2024
• Northbound
– Begin tree clearing.– Continue Phase 2 mainline drainage and widening work.