Nashua - Merrimack - Bedford 13761
>> Click here for latest News Release
Recent Activities – As of early February 2023
• Northbound
– Installed delineators on mainline• Southbound
– Continued blasting and excavation of ledge on the mainline south of US Rt. 3 bridge– Installed silt fence, portable barrier, and water diversions
– Began placing embankment south of the ledge cut and installing drainage structures along mainline
Upcoming Work – February 2023 to March 2023
• Northbound
– Continue installing signs and delineation• Southbound
– Continue blasting operations and ledge work through the winter– Continue drainage and embankment installation north of US Rt. 3 bridge
General Traffic Implications
• Winter 2022-2023
– Trucks will access work areas using mainline shoulders– Lane closures on mainline from February 2023 to April 2023