Project Schedule

Nashua - Merrimack - Bedford 13761

 

2016-2018

  • Public Officials Meeting
  • Develop Design Alternatives
  • Research Environmental Resources

2018

  • Hold Public Informational Meetings
  • Evaluate Design Alternatives
  • Evaluate Environmental Impacts (wetlands,
    water quality, noise, etc.)
  • Publish Environmental Study
  • Public Hearing

2018-2021

  • Final Design
  • Right of Way Acquisitions / Easements
    Environmental Permitting

2022

  • Anticipated Start of Construction