Construction Updates


Nashua - Merrimack - Bedford 13761

>> Click here for latest News Release


Project 13761D

Turnpike Widening near NH 101/I-293 Interchange

Recent Activities – As of early April 2024

• Northbound and Southbound
– Continued preparing for granite curb installation on FEET northbound ramps.
– Installed end sections on drainage pipes.
– Installed conduit for ITS system.
– General site cleanup

Upcoming Work – April 2024 to May 2024

• Northbound and Southbound
– Raise frame and grates for drainage structures.
– Continue preparing for and granite curb installation and installing granite curb.
– Construct earth berm along FEET southbound.
– Continue work on ITS tower.
– Continue installing signage.
– Install fencing.
– Final paving and striping.

General Traffic Implications

• Spring 2024
– All three NB and SB lanes open to traffic
– Shoulder and lane closures as needed for minor work

Recent Photos of Construction

100
99
98
97
96
95
94
93
92
91
90
89
88
87
86
85
84
83
82
81
80
79
78
77
76
75
74
73
72
71
70
69
68
67
66
65
64
63
62
61
60
59
58
57
56
55
54
53
52
51
50
49
48
47
46
45
44
43
42
41
40
39
38
37
36
35
34
33
32
31
30
29
28
27
26
25
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1

Pier Protection Barrier Installation – February 2024
Median Barrier Installation – February 2024
Installed Right-of-Way – February 2024
Installed Overhead Signs – February 2024
Installed Ground Mounted Signs – February 2024
Installing Right-of-Way Fence – January 2024
Finalizing Grading of Ramp Infield Berm – January 2024
Casting Median Barrier Transitions – December 2023
Paving Adjacent to Median Barriers – December 2023
Grinding and Striping NB High Speed Lane – December 2023
Milling of Drainage Structure Patches – December 2023
Installation of Traffic Signs – December 2023
Installation of Overhead Sign Structure – December 2023
Pavement Repairs to Drainage Trenches – December 2023
Pouring Foundation for ITS Antenna – November 2023
Paving SB High Speed Lane and Median – November 2023
Milling of SB High Speed Lane – November 2023
Traffic Sign Foundation Construction – November 2023
Paving High Speed Lanes – November 2023
Placing Median Barrier – November 2023
Adjusting Drainage Structure Grates – November 2023
Filling Abandoned Drainage Structures – October 2023
Completing Patching of Drainage Trenches – October 2023
Video Inspection of Completed Drainage Structures - October 2023
Drainage Structure Installation – October  2023
Bituminous Curb Installation – September 2023
Attenuator Installation – September 2023
Hydroseeding Operation – September 2023
Paving Operations on SB Mainline – September 2023
Placing Temporary Barrier on SB Roadway – September 2023
Removal of Median Barriers along Mainline – September 2023
SB Guardrail Installation Work – August 2023
SB Milling Operations – August 2023
Adjusting Drainage Structure Along SB Mainline – August 2023
Temporary Barrier Along NB Mainline – August 2023
Mounting Equipment on NB ITS Tower – August 2023
Seeded Area Along SB Mainline – August 2023
Roadway Select Materials Along SB Mainline – August 2023
SB Geogrid Installation Work – July 2023
SB Geogrid Installation Work – July 2023
SB Geogrid Installation Work – July 2023
SB Geogrid Installation Work – July 2023
SB Drainage Work – July 2023
Construction of Foundation for NB ITS Tower – July 2023
Construction of Foundation for SB Overhead Sign Structure – July 2023
Finished NB Ledge Work – June 2023
Pavement Patch Work – June 2023
Placing Roadway Select Materials Along NH 101 EB On-Ramp – June 2023
Constructing NB Overhead Sign Structure Foundation – June 2023
SB Ledge Excavation and Drainage Work – June 2023
SB Ledge Excavation Work – May 2023
SB Blasting Operations – May 2023
Temporary NH 101 EB On-Ramp – May 2023
SB Drainage Work – May 2023
SB Ledge Excavation Work – May 2023
Right-of-Way Fence Along NB Mainline – May 2023
Making Roadway Select Materials Adjacent to SB Travel Lanes – April 2023
Tree Clearing for Placing Right-of-Way Fence Along NB Mainline – April 2023
Installing Right-of-Way Fence Along NB Mainline – April 2023
SB Ledge Excavation Work – April 2023
NB Grass Establishment – April 2023
SB Drainage Work – April 2023
SB Ledge Excavation Work – March 2023
SB Ledge Excavation Work – March 2023
SB Ledge Excavation Work – March 2023
SB Drainage Work – February 2023
SB Rock Excavation Work – February 2023
SB Embankment Work – February 2023
SB Drainage Structure Installation – February 2023
Roadway Select Materials Adjacent to NB Travel Lanes – January 2023
Guardrail on NH 101 EB On-Ramp to NB Mainline – January 2023
SB Ledge Excavation Work – January 2023
SB Ledge Excavation Work – January 2023
SB Ledge Excavation Work – January 2023
Paving NB Travel Lanes – December 2022
Rock Crushing to Select Materials – December 2022
Pavement Markings on NB Travel Lanes – December 2022
Installing Channel Matting Adjacent to NB Travel Lanes – November 2022
Rock Crushing to Select Materials – November 2022
Nighttime Milling Operations on NB Travel Lanes – November 2022
Stormwater Treatment Basin – November 2022
Temporary NH 101 EB Off-Ramp – November 2022
NB Pavement Operations – November 2022
Installing Anti-Seep Collars Within Stormwater Treatment Basin – October 2022
Placing Low-Permeability Fill Within Stormwater Treatment Basin – October 2022
Installation of Conduit for Highway Lighting Adjacent to NB Travel Lanes – October 2022
Fine Grading Adjacent to NB Travel Lanes – October 2022
Rock Crushing to Select Materials – October 2022
Stormwater Treatment Basin - August 2022
Drainage installation Adjacent to NB Travel Lanes - August 2022
Blasting Operations (pre-split wall) to Remove Ledge Adjacent to NB Travel Lanes - August 2022
Rock Removal Adjacent to NB Travel Lanes - August 2022
Rock being removed from the road after a blast - August 2022
Rock crushing to select materials - August 2022
Blasting Operations to Remove Ledge Adjacent to NB Travel Lanes - July 2022
Blasting Operations to Remove Ledge Adjacent to NB Travel Lanes - July 2022
Blasting Operations to Remove Ledge Adjacent to NB Travel Lanes - July 2022
Overhead sign structure removal on F.E. Everett Turnpike south of US Rt.3 bridge - June 2022
Temporary ramp and drainage installation on NH 101 on-ramp to Southbound F.E. Everett Turnpike - June 2022
Tree clearing along Northbound F.E. Everett Turnpike south of US Rt.3 bridge - June 2022