Construction Updates

Nashua - Merrimack - Bedford 13761

>> Click here for latest News Release

Project 13761E

Turnpike Widening from Exit 12 (Bedford Road) to the Bedford Toll Plaza”

Recent Activities – As of early November 2024

• Median
– Completed installing pavement in the median.
– Completed installing median barrier.
– Placed traffic on median pavement.

• Northbound
– Removed temporary guardrail and temporary pavement.
– Began soundwall construction.
– Began overhead sign foundation construction.
– Began grading crushed stone.

• Southbound
– Removed temporary guardrail and temporary pavement.
– Began soundwall construction.
– Began BMP access road and berm.
– Began grading crushed stone.

Upcoming Work – November 2024 to December 2024

• Northbound
– Finish soundwall.
– Finish overhead sign foundation.
– Place pavement.

• Southbound
– Finish BMP access road and berm.
– Place pavement.

General Traffic Implications

• Fall 2024
– Rolling roadblocks and shoulder closures, as needed, for temporary roadwork, as traffic allows

Recent Photos of Construction

39
38
37
36
35
34
33
32
31
30
29
28
27
26
25
24
23
22
21
20
19
18
17
16
15
14
13
12
11
10
9
8
7
6
5
4
3
2
1

Paved Median Prior to Traffic Shift - November 2024
BMP Access Road Construction - November 2024
Removing Temporary Pavement - November 2024
Soundwall Construction - November 2024
Overhead Sign Foundation Construction - November 2024
Paving Median - October 2024
Paved Median - October 2024
Median Barrier Construction - October 2024
Median Drainage Installation - September 2024
Median Excavation and Drainage - September 2024
Median Construction - September 2024
Rock Excavation in Median - September 2024
Old Drainage Removal in Median - September 2024
Median Construction at Dumpling Brook Crossing - August 2024
Median Excavation - August 2024
Median Drainage Installation - August 2024
Median Construction at Dumpling Brook Crossing - July 2024
Removing Existing Pavement - June 2024
Removing Existing Pavement - June 2024
Construction of Northbound Temporary Widening - May 2024
Fine Grading of Northbound Temporary Widening - May 2024
Construction of Southbound Temporary Widening - May 2024
Installing Soundwall Drilled Shaft Foundations - February 2024
Installing 42 in. Culvert at Dumpling Brook - January 2024
Installing 42 in. Culvert at Dumpling Brook - January 2024
Grading and Construction of Soundwall Berm - December 2023
Temporary Cofferdam near Dumpling Brook Culvert - December 2023
Winter Stabilization Application Along Ledge Cuts - December 2023
Blasted Rock Ready for Removal - November 2023
Completed Stormwater Treatment Basin 1188 - November 2023
Placement of Select Materials along NB Roadway - November 2023
Southbound grading work near the ledge removal area - October 2023
Excavation work at Detention Basin 1188 - October 2023
Excavation and Fill Placement along SB Roadway - September 2023
Deep Pipe Installation - September 2023
Trenching across the Turnpike for new Pipe Culvert - September 2023
Trenching across the Turnpike for new Pipe Culvert - September 2023
Excavation and Shaping of Detention Basin 988 - August 2023
Stripping Topsoil - August 2023
Tree Clearing Work - August 2023
Tree Clearing Work - August 2023
Tree clearing Work - August 2023