2016-2018 |
- Public Officials Meeting
- Develop Design Alternatives
- Research Environmental Resources
|
2018 |
- Hold Public Informational Meetings
- Evaluate Design Alternatives
- Evaluate Environmental Impacts (wetlands, water quality, noise, etc.)
- Publish Environmental Study
- Public Hearing
|
2019-2025 |
- Final Design
- Right of Way Acquisitions / Easements
- Environmental Permitting
|
2022 |
- Start of Construction for the 13761D Project Northern Segment (F.E.E.T. Widening of 2-lane Section North of Exit 13, in Merrimack, to North of I-293 Diverge, in Bedford) Location Map , Plan View , Construction Update
|
2023 |
|
2024 |
- Anticipated Start of Construction for the 13761A Project Southern Segment (F.E.E.T. Widening of 2-lane Section North of Exit 8, in Nashua, to South of Exit 10 in Merrimack) Location Map Plan View (Coming Soon)
|
2025 |
- Anticipated Start of Construction for the 13761B Project, Bridge Replacements (Replace Baboosic Lake Road Bridge over F.E.E.T. and Replace Wire Road Bridge over F.E.E.T. in Merrimack) Location Map, Plan View (Baboosic Lake Road), Plan View (Wire Road)
- Anticipated Start of Construction for the 13761C Project, Middle Segment (F.E.E.T. Widening of 2-lane Section North of Exit 11 to North of Exit 12 in Merrimack) Location Map
|